The COUNTY ADMINISTRATION CENTER AND ADJACENT PARKING STRUCTURE project is to be completed in an approximate three-year schedule of activities. The project is to be built using the "Design/Build" process in which the Solano County Department of General Services contracts with a single, combined team of architects, engineers and builders to design and construct the project, as opposed to contracting separately with each of these entities. This is a process that allows public buildings to benefit from collaboration of the entire design and construction team from the outset while preserving cost competition and quality control. This process compresses the time frames between design and construction, allowing a more efficient, rapid completion of the project. This format requires a somewhat different set of phases than the traditional sequence of designing, bidding and then building, each of which is described as follows.
Prepare Draft Environmental Impact Report (DEIR)
1/17/02 - 6/7/02 (completed)
Government Agency & Public Comment Period
7/9/02 - 8/22/02 (completed)
Prepare Final Environmental Impact Report (FEIR)
8/23/02 - 9/22/02 (completed)
County Board of Supervisors Certify & Adopt FEIR
10/1/02 (completed)
Issue Master Architect Notice to Proceed
11/21/02 (completed)
Programming of County Departments Phase
11/26/02 - 3/4/02 (completed)
Master Planning & Concept Design Phase
12/10/02 - 2/5/02 (completed)
Preliminary Bridging Documents Phase
2/1/02 - 5/16/02 (completed)
Final Bridging Documents Phase
4/29/02 - 8/21/02 (completed)
Develop Request for Qualifications (RFQ) Package
3/6/02 - 6/6/02 (completed)
Issue Request for Qualification
6/7/02 (completed)
Mandatory Pre-Submission Conference
6/21/02, 10:00 a.m. PST (completed)
Last Date for Submission of Questions
7/5/02, 4:00 p.m. PST (completed)
SOQ Submission Due Date
7/19/02, 4:00 p.m. PST (completed)
Short List to Five (5) to Seven (7) Design Builders
8/2/02 (completed)
Interview of Short Listed Firms
8/16/02 (completed)
Issue Request for Design Build Proposals
8/23/02 (completed)
Mandatory Pre-Proposal Conference
9/6/02 (completed)
Design Builder Proposals Due
10/25/02 (completed)
Design Builders Presentation of Proposals
10/30/02 (completed)
Announce Selected Design Builder
11/5/02 (completed)
Design Builder Notice to Proceed
11/19/02 (completed)
Design and Construction Phase
11/19/02 - 3/1/05 (started)
SOLANO MASTER PROJECT SCHEDULE (PDF)